Final Pipe Connects Fitzroy to Gladstone

Posted By Utility Magazine,
06/11/2025 12:00 PM
The last pipe has been installed for the 117km Fitzroy to Gladstone Pipeline (FGP), which is now set to deliver a secure water future for the region.  The Fitzroy River is now officially connected to Gladstone’s water network and water is set to flow through the $983 million pipeline as early as 2026.  The first pipe was delivered to Gracemere in June 2023 and 3 November 2025 marks the completion of the pipeline installat...